How a PMP result is reported
PMP
The PMP result is pass or fail. The report uses four ratings. A pass starts a three-year cycle of 60 units.
Pass or fail
When you complete the Project Management Professional (PMP) examination, your final outcome is reported simply as a pass or a fail. The Project Management Institute (PMI) does not publish a target percentage or a fixed number of questions you must answer correctly to pass.
Subject-matter experts set how many scored questions must be answered correctly. Each scored question is worth one point, and the score is the total of those points. Of the 180 questions on the exam, 10 are unscored pretest items. These 10 items are placed at random throughout the test, so you cannot identify them, and they do not influence your final score.
Your performance is evaluated across four rating categories:
- Above Target: Your performance exceeds the minimum requirements for the exam.
- Target: Your performance meets the minimum requirements for the exam.
- Below Target: Your performance is slightly below the minimum requirements and does not meet the passing standard.
- Needs Improvement: Your performance is far below the minimum requirements and does not meet the passing standard.
Both Below Target and Needs Improvement represent failing ratings. According to the sample exam result report, your report also breaks down your performance across each domain using these same four categories. This diagnostic breakdown is provided even when you pass, allowing you to see where your knowledge was strongest and where it was weaker. PMI states that these domain ratings exist to guide preparation and should never be used by employers to make hiring decisions.
If you test on a computer, the result shown on your screen at the conclusion of the session is strictly preliminary. The PMI Certification Handbook states that official examination reports are posted to your online account no later than 10 business days after your test date, and PMI will send an email when your official report is ready to view. Who can apply is on the PMP guide.
If you do not pass
PMI allows you up to three exam attempts within your one-year eligibility window.
There is a slight difference in how this rule is described across official resources. PMI's general website summarizes the policy by stating that you may take the exam up to three times in one year. The July 2026 examination content outline provides the full operational rules for testing limits:
- After a third attempt without a pass: You wait one year from the date of the last exam before you apply again.
- If the eligibility year ends with attempts left: You apply again. There is no extra one-year wait. The experience you report still has to fall inside the 10-year window.
After a pass
Passing the exam marks the start of your Continuing Certification Requirements (CCR) cycle. According to the CCR Handbook, your cycle begins on the exact day you pass the exam and runs for three years.
To keep your certification active, you must earn 60 Professional Development Units (PDUs) within that three-year cycle. One PDU equals one hour spent learning, teaching, presenting, reading, volunteering, or creating content. PMI divides these units into specific categories:
- Education: You must earn at least 35 PDUs in educational activities.
- The Talent Triangle: At least 8 of the 60 units must fall in each area: Ways of Working, Power Skills, and Business Acumen.
- Giving Back: You may count a maximum of 25 PDUs toward your total by giving back to the project management profession.
Once the 60 units are recorded and PMI confirms they meet the requirements, there is a renewal fee. It is separate from a PMI membership fee. This page does not list the amount. The certification is renewed every three years through this programme. How the exam is organised is on the PMP guide.